Item Coversheet



Staff REPORT
Action ITEM

Item # 11.b.

SUBJECT: 

Proposed Budget Adjustment to change Hirst Reservoir CIP Project from USDA Loan Funding to Cash (E. Krens) pgs. 58-61

DATE OF MEETING:  

November 9, 2021

Staff CONTACT(S):

Elizabeth Krens, Director of Finance

Linda Jackson, Financial Analyst




SUMMARY and RECOMMENDATIONS:

During the October 12th meeting, Town Council directed staff to prepare a budget adjustment to realign the funding source for the Hirst Reservoir Improvements capital project from USDA loan to cash. Staff recommends Council adopt BA 22-008 to amend the project’s funding source to use of cash reserves totaling $1.445m.

BACKGROUND:

The Town Council adopted the FY22 budget on June 8, 2021. The budget’s Capital Improvement Plan (CIP) identified USDA loan as the funding source for several projects: Hirst Reservoir Improvements, WTP to Town Water Main, Reservoir to WTP Raw Main. In recent discussions regarding the Hirst Reservoir project, Council indicated a desire to amend the project’s funding source from loan to cash reserves. The funding for the other projects will be discussed in more detail during the ARPA/CIP work session on November 17.



ISSUES:

As of 6/30/21, the Water Fund’s cash balance totaled $6.3m or $3m available above fiscal policy limits (100% of operating expenditures and debt service). After reviewing proposed use of cash in the FY22 budget, Water Fund cash reserves are sufficient to support the Hirst Reservoir Improvement project costs of $1.445m.  After adoption of BA 22-008, $1.6m in Water Fund cash will be available beyond fiscal policy requirements for future uses.

 

A public hearing is not required as there is no change to the total FY22 appropriation.



BUDGET IMPACT:

There is no budgetary impact as this action is limited to realignment of funding sources.



MOTION(S):

“I move the Town Council approve Budget Adjustment BA 22-008 to amend the Hirst Reservoir Capital project funding source from USDA loan to cash reserves totaling $1.445m.”



ATTACHMENTS:
Description
BA 22-008
FY22 Water CIP Funding Summary